Everything posted by davidw
-
Banshee Construction Progress
looks like they are back working on the 2nd wing of the batzel lowing.
-
Banshee Construction Progress
Despite the weather, the crew was able to install 2 supports today. Link to gallery
-
Banshee Construction Progress
Soooo, I'd say its snowing today. (removed pic)
-
Banshee Construction Progress
Four pieces of track installed today. Link to gallery
-
Banshee construction time lapse
Week 22 (12/23/13 - 12/29/13): -
-
Banshee Construction Progress
Crew works hard on Sundays too. Four supports and one piece of track installed. Link to gallery
-
Banshee Construction Progress
One support and 3 pieces of track installed. First half of The Bat wing is complete. Link to gallery
-
Banshee Construction Progress
that will probably be the last portion they work on. B&M coasters are usually built sequentially.
-
Banshee Construction Progress
one support and one piece of track installed today. Link to gallery
-
Banshee Construction Progress
My computer rebooted without me knowing yesterday, so I wasn't able to watch the captures like I normally would for this update. But from what I can tell, 1 support and 3 pieces of track were installed today. Link to gallery
-
Banshee construction time lapse
Week 21 (12/16/13 - 12/22/13): -
-
Banshee Construction Progress
Due to high winds, not much progress today. Only 1.5 supports installed today. It was an oddly shaped support that has three legs support that actually supports 2 pieces of track. As always, Link to gallery.
-
Site Suggestion
i actually really like how coaster buzz does it. they have a "floating" menu that follows you down the page.
-
Banshee Construction Progress
^ you can see an archive of my webcam captures with the link in my signiture
-
Banshee Construction Progress
3 supports and 3 pieces of track installed again today. As always, Link to gallery.
-
Banshee Construction Progress
3 supports and 3 pieces of track. Link to gallery
-
Banshee Construction Progress
Good progress today. 5 supports and 4 pieces of track. Link to gallery
-
Banshee Construction Progress
. <delete this post>
-
Banshee Construction Progress
wow, already 4 supports installed, and they've only been at it for about an hour
-
Banshee construction time lapse
Week 20 (12/09/13 - 12/15/13): -
-
Banshee Construction Progress
could just be for proximity sensors?
-
Banshee Construction Progress
I know someone asked this before... judging by those pics, it doesn't look like the lift hill chain is installed yet
-
Banshee Construction Progress
From my uderstanding, there wont be a true MCBR, but it looks like the final brake run will be longer. This should allow them to use 3 trains. The only electric i can think that they would have back there would be lights.
-
Banshee Construction Progress
I think the fact that they aren't doing much on the back half or the coaster is a sign that there isn't going to be trim brakes? If they had to run the electrical to those, you would think they would want the track in place as fast as they could.
-
Banshee construction time lapse
Week 19 (12/02/13 - 12/08/13): -