First post, here goes-
I did a little digging into the Notice of Commencement that was filed with Warren County for the "2018, 2019, and 2020 Additions and Modifications for Kings Island Park". I compared this document with the one that was filed for the 2016-2017 modifications, which included GCI for Mystic Timbers. I noted if the company was present in the 2016 document, their field of work, and notable things they've done in the park if I could find them.
Company
Area of Work
2016-2017?
Notable Work?
EXHIBIT 3 FABRICATIONS LLC
Signage
Y
Haunt Sign, Reds Grille Sign
PLAS PLUMBING
Plumbing
Y
Paramount's KI Site Utilities
PATRIOT INDUSTRIAL CONTRACTING SERVICES INC
Rigging/Moving
Y
Winterfest Eiffel Tower Lighting Rigging
QUEEN CITY AWNING
Awnings
Y
KINGDOM PRODUCTION INC
Theming/Signage
Y
BAYNUM PAINTING
Ride Painting
Y
Firehawk (2007) Vortex (2008), The Bat (2015)
PAINTING CONTRACTOR LLC
Interior Painting
Y
DALLAS FLOORING
Interior Flooring
Y
MODERN DAY CONCRETE CONST
Concrete
Y
ASHLEE FENCE ENTERPRISES
Fencing
Y
OHIO HYDRAULICS INC
Hydraulic Hoses/Fittings
Y
HICON INC
Stone Paving/Masonry
Y
CARDINAL LANDSCAPE
Landscaping
Y
DENIER ELECTRIC COMPANY
HV Electrical
Y
Drop Zone, Diamondback
T S GARNETT CONST INC
Excavation
Y
BREHOB ENGINE & COMPRESSOR CO
Air Compressors
Y
Most rides in 2018
KONE INC
Elevators
Y
JOHN R JURGENSEN COMPANY
Paving/Aggregates
Y
BEACON ELECTRIC INC
HV Electrical
Y
Banshee (2014)
SCHMIDT PROGRESSIVE LLC
Fiberglass display fixtures
Y
REFLECT SYSTEMS INC
Digital Signage
Y
Entrance Turnstile Displays
TRUE EDGE INC
Metal Fabrication
Y
R E MIDDLETON CONST
Concrete
Y
WindSeeker Foundations
PERKINS/CARMACK CONST
General Contracting
Y
Mystic Timbers Entrance/Photo, Funnel Cake Building
QUEEN CITY BLACKTOP
Paving
Y
CAMPEON ROOFING INC
Roofing
Y
FENTON RIGGING CO
Ride Erection/Rigging
NO
TRIDENT ENGINEERING INC
Pumps/Water Ride Install
NO
Diamondback Splashdown, Tasmanian Typhoon
BOLLINGER & MABILLARD
Coaster Design/Engineering
NO
Diamondback, Banshee
You can see that we have B&M listed, but note the other two additions- Fenton Rigging and Trident Engineering. Fenton did ride erection back in the Paramount days, though I'm not sure on which rides specifically. Trident Engineering does water pump engineering, most recently at KI the splashdown at the end of Diamondback. There is another rigging company listed, but they seemed to have only been used for hanging the Eiffel Tower lights for Winterfest.
In 2014, the Adena Corporation out of Mansfield, OH was the steel erector and general contractor for Banshee, a B&M project. Since then, they have also installed Diamondback, Intimidator 305, Maverick, GateKeeper and Valravn. We don't see Adena Corp listed on the Notice of Commencement, but it is possible that they are contracted by B&M directly, not through the park. This leads me to believe that Fenton may be the contractor which will be removing whichever coaster it turns out to be. If that were the case, it is unlikely that it would be scrapped, otherwise a demolition company would be listed instead, like it was in 2014 when O'Rourke Wrecking was contracted to demolish Son of Beast.
TLDR: No demolition/scrapping company was listed on the Notice Of Commencement, which could mean a relocation instead of demolition.